Chinese enterprises to build the Bangladesh national power grid upgrading turnkey project first line 8 officially put into operation to send power, marking the northwest of Bangladesh Rajshahi regional power grid transmission capacity has been greatly enhanced.
According to reports, the scope of the project covers 99 substations and about 1,000 kilometers of transmission lines within the jurisdiction of the Bangladesh National Power Grid Company, new construction, expansion, upgrading, renovation, etc., by the Export-Import Bank of China to provide preferential buyer’s credit, China Electric Power Construction Group Fujian Engineering Corporation, Beijing, China Cable & Tongda Electrical Sets Co.
It is reported that the project will effectively improve the Bangladeshi power grid after commissioning and transmission of electricity, so that the power grid to realize the closed loop of 132 kV and 230 kV ring network, and help the Bangladeshi power grid to achieve stable operation and transmission loss reduction targets.